Winter 2000
Minerals Development
Gas production wells and pipelines rejected
due to impact on green belt and landscape.
Independent Energy UK (now in receivership) has failed in its proposal
to drill wells and extract natural gas over a period of at least 13
years from a reserve beneath upland farms in Staffordshire and transport
it via a five-kilometre pipeline to an existing generating facility.
The main issue was whether the development was appropriate within a
green belt area, with visual impact a further concern. The inspector
thought that the wellhead would harm the landscape be virtue of proposed
screening mounds, 330 metre access track and a 35 metre rig. He said
that the scheme would fail to maintain the openness of the area and
fail to achieve high environmental standards.
He concluded that the information submitted in support of the pipeline
was inadequate in terms of assessing its environmental impact.
The appellant has proposed a 30 metre corridor within which the pipeline
could be located. The minerals planning authority argued that, following
the 1989 judgment in Barratt Luton Ltd v Secretary of State for the
Environment and Mid Bedfordshire District Council, once the principle
of the route was established by the grant of permission, it would then
have no scope to refuse all routes along the corridor once its environmental
acceptability had been agreed. The inspector accepted that the information
required to assess the impact was insufficient to allow the grant of
a full planning permission.
He took the view that the harm arising from the scheme outweighed any
national need for the extraction of natural gas and that very special
circumstances had not been demonstrated. He also refused an award of
costs in favour of the appellant, despite the fact that officers had
recommended a temporary permission.
OPENCAST COAL MINING DECISION
Complaints by local residents in respect of a decision by Barnsley Metropolitan
Borough Council to grant permission for opencast mining have not been
upheld. Residents argued that the council publicised the application
in a misleading manner, failed to adequately assess the environmental
effects and was given inaccurate information by officers. In particular,
the complainants argued that advice to councilors that they might be
liable for personal surcharges of approximately £300,000 should
the application be refused on grounds which could not be substantiated
amounted to maladministration.
The ombudsman held that the complaints should not be upheld since it
was appropriate for officers to impress upon councilors why an application
should be approved and the possible consequences of not doing so. There
could be no criticism of this advice and the complaints were rejected.
SCOTTISH MINISTERS FOUND TO BE IN BREACH OF DUTY
Redland Aggregates have been successful in getting the Scottish courts
to judicially review the failure of the Scottish ministers to issue
a decision in respect of its proposed coastal super-quarry on Harris
in the Western Isles. The Company's representatives told the court that
since the initial submission of the planning application in 1991, nine
and a half years had elapsed. The reporter had issued a draft report
in 1998, almost three years after the close of the public inquiry into
the scheme, and the Scottish ministers had received the final report
in April 1999.
The Company further argued that the suggestion by the Scottish ministers
that the site should be considered to be potentially worthy of being
designated a Special Area of Conservation under the European habitats
directive before issuing a decision on the application was procedurally
improper, particularly since Scottish Natural Heritage (SNH), the ministers'
adviser on such matters, had been one of the principle objectors to
the super-quarry scheme.
Lord Justice Hardie concluded that while there was no statutory period
for allowing ministers to determine an application, the company had
a legitimate expectation that it would be determined within a reasonable
period. In this case he commented, the delay was of "scandalous
portions".
The judge also held that the minister' actions in referring the possible
designation to SNH had been unlawful since the latter could not be seen
to provide an impartial opinion. The ministers had breached the company's
right under article 6 of the European Convention on Human Rights which
entitled it to a fair and public hearing within a reasonable period
by an independent and impartial tribunal, he ruled.
QUARRY PROJECT IS TURNED DOWN
Plans for a super-quarry on the island of Harris were rejected recently
by Scotland's new environment minister, Sam Galbraith, who said that
a recommendation to approve the scheme had placed too much emphasis
on English planning guidance.
Galbraith turned down operator Lafarge Redland Aggregates' application
for a 459ha quarry on the grounds that the adverse environmental effects
outweighed the need to meet English stone demand. He was overruled the
findings of the reporter Gilllian Pain, who recommended in March 1999
that the economic and social benefits of the development at Lingerbay
were of national importance and superseded environmental concerns.
Galbraith said the reporter was wrong to use the DETR's Mineral Planning
Guidance on aggregates provision in England (MPG6) as a material consideration
in the case and criticised her for having "seriously understated
the impact of the development on the national scenic area".
MPG6 suggests that in order to meet aggregate demand in England, a shift
in focus from English sites to remote quarries in Scotland is required.
But Galbraith said that Scottish planning guidance should have been
the primary concern.
Kevin Dunnion, director of campaign group Friends of the Earth for Scotland,
said the decision was "real evidence that the Scottish Executive
is prepared to give a higher priority to the environment".
Graham U'ren, director of the RTPI in Scotland, said : "This highlights
the need for a UK wide framework in which major judgments such as this
can be made". Lafarge Redland director John Leivers said the company
was "extremely disappointed".
|
Mine shaft vent
Coal disposal point
|